Jieyang · 800 mm rotary piling · 5–9 June 2025

High-spiral core barrel tested in granite.

DRILLNOVA · Field report · Updated

The customer was concerned about heavy roller-bit wear and accumulated cuttings. We designed and manufactured an 800 mm high-spiral core barrel with revised cutter spacing, then followed its use with the site crew.

The trial brought encouraging feedback on cuttings discharge, a reported response to operating adjustments and a clear next step for core recovery. Here is how the design was tested, what came out of the hole and what the records showed.

See the trial findings →

The 800 mm high-spiral barrel during the Jieyang field trial.
The 800 mm high-spiral barrel during the Jieyang field trial.

A barrel designed around the customer’s problem.

The site had small-diameter piles with substantial rock drilling. Existing guides were heavily worn, and the review found periods of thick or insufficient slurry and material accumulating around the cutting system. The customer needed a practical response to short roller-bit life, rather than another replacement supplied without investigating its use.

Our trial design combined a higher spiral with revised spacing around the roller bits. The purpose was to help move cuttings away from the cutting face and improve slurry movement, with better penetration and service life as the goals to test.

Trial barrel · the high spiral around the shell was designed to assist cuttings movement.
Trial barrel · the high spiral around the shell was designed to assist cuttings movement.
Trial cutting assembly · the roller-bit spacing was reviewed as part of the same design.
Trial cutting assembly · the roller-bit spacing was reviewed as part of the same design.
What the team found on the existing site tools

These are older conventional barrels inspected during the wider visit, not the new high-spiral trial barrel. Worn guides and replacement work helped explain why the review covered the steelwork, slurry and operating practice together.

Worn guides on an older conventional barrel at Jieyang
Worn guides on an older site barrel inspected during the wider visit.
Site worker replacing a roller bit on an existing Jieyang barrel
On-site roller-bit replacement on an existing conventional barrel.

Understand the rock before judging the tool.

The site account describes dense granite, with boulders, inclined rock faces and soil or sand interlayers. Conditions changed between nearby piles. The team examined recovered material alongside the pile log, because vibration, cutting response and core recovery depended on what each hole encountered.

Recovered rock and cores from the Jieyang field visit. This wider view provides ground context; it is not assigned to a single depth interval.
Recovered rock and cores from the Jieyang field visit. This wider view provides ground context; it is not assigned to a single depth interval.
7 June · rock fragments recovered during the late-morning trial. The team checked the returned material alongside the pile record.
7 June · rock fragments recovered during the late-morning trial. The team checked the returned material alongside the pile record.

Two tested site samples

Uniaxial compressive strength · laboratory results filed with the site record
SampleRecorded strengthMoisture condition
Rock sample 192.2 MPaNatural
Rock sample 2129 MPaNatural

These are individual results for two tested samples. Sampling depths were not entered, so the values are not assigned to every photograph or to the full drilling interval.

Follow the barrel from first entry into drilling.

First check: was the new barrel cutting or reaming?

On 5 June, the first lowering was into a smaller hole already cut with a bullet-tooth barrel. After about 1 m of reaming, the team discussed the fit with the crew and moved the trial to a fresh pile. That decision kept the first fit-up operation separate from new rock penetration.

The rigs and tools at Jieyang. The trial moved between machines, so readings were kept with each pile entry.
The rigs and tools at Jieyang. The trial moved between machines, so readings were kept with each pile entry.

Record the operating response with the crew

The follow-up tracked lowering, cutting, lifting and re-entry. For example, the 5–6 June overnight entry recorded 5.83 m of advance, with head speed measured at 14–15 r/min. On 6 June another rig drilled under assembly weight without additional crowd. These observations helped the discussion move from a general wear complaint to the actual use of the barrel.

The site summary reports that combined feed and rotary-speed adjustments raised the observed pure-cutting rate from the earlier 0.2–0.3 m/h to about 0.35 m/h. It was an encouraging field response, though below the team’s target. The readings below show the different rigs and stages; they are not a single operating recipe.

Recorded rig settings and operating stages
Jieyang · recorded settings at identifiable stages
Stage / rigDepth or work, mHead speed, r/minP4 indication*Field action
5 June · A3-11-2 / machine 18≈1 m reaming; exact endpoints not recorded12Not recordedEnlarging the earlier bullet-tooth hole; then move to a fresh pile.
5–6 June · ZH-16 / machine 38.90 → 14.73 m14–15, field-measuredNot recordedOvernight rock drilling; tool lifts recorded at 20:55 and 22:04.
6 June, 11:11 · ZH-30 / machine 139.94 m checkpointNot recordedNot recordedNo additional crowd applied; drilling under assembly weight.
7 June, 11:06 · Zz-K4G2-16 / machine 1012.32 m checkpoint92.7; unit omittedE mode, steady rock entry; wire-rope entry 5 t and Y-axis entry “0.2 -0.3” (sign/range and unit unconfirmed).

P4 is a hydraulic feed-pressure indication, not a direct measurement of load at the cutting face. Readings with missing units are retained as recorded. Read the separate adjustment summary and proposed next check.

From the recovery attempt to the rock brought up.

On the morning of 7 June, machine 10 advanced from 16.46 to 17.03 m in the recorded pile entry. The crew reported high cutter temperature and strong vibration near the end of the run. The following recovery sequence shows the actual material brought to the surface.

 First attempt · 7 June  The recovery tool brought up mud. Discharged material is visible beside the rig.
First attempt · 7 June
The recovery tool brought up mud. Discharged material is visible beside the rig.
 Second attempt · the same pile  Rock was recovered beside the rig; the site note describes inclined rock.
Second attempt · the same pile
Rock was recovered beside the rig; the site note describes inclined rock.

The second attempt produced a visible rock recovery result. The first-attempt video below shows the preceding mud discharge. Together, the two attempts show why recovery performance needed to be assessed separately from cutting.

First core-recovery attempt · 16 secondsOriginal Jieyang footage · lifting the recovery tool and discharging mud.
What this footage shows

The recovery tool is lifted and wet material is released beside the rig. This footage belongs to the first attempt in the machine-10 record. The photograph in the two-attempt comparison above shows the rock recovered on the second attempt.

What the recovery sequence told us

The roller-bit barrel cut the rock; a separate recovery tool was used to grip and remove it. An earlier overnight entry had already brought the operator’s feedback that cuttings discharge was good but that recovering a core after a short advance was difficult. This showed why the next improvement needed to include core gripping and unloading, alongside the high-spiral cutting barrel.

The team proposed reviewing the recovery tool’s internal gripping arrangement and discharge geometry. That was a follow-up design recommendation; this trial does not record a completed recovery-tool redesign.

View this pile’s original time and depth record →

Keep the roller-bit checks with the drilling record.

Follow-up continued beyond the first run. The team photographed the cutters on 7 June at 17:00, then recorded hand checks of cone rotation at 09:30 on 8 June. These inspections formed part of the trial, alongside the running depth record and conversations with the operators.

Roller-bit condition at the Jieyang inspection labelled 7 June at 17:00
7 June · 17:00 inspection. The team photographed the cutters during the trial before continuing the follow-up.
8 June, 09:30 · rotation check · 31 secondsOriginal Jieyang footage · several roller bits checked by hand.
What this footage shows

The inspection moves between several cutters, showing attached material and hand checks of cone rotation. This is a dated inspection of the barrel; individual cutter IDs were not recorded, so it does not prove the same cutter appears in both dated views.

The longest detailed pile entry ran from 6.85 to 20.93 m between 7 and 9 June: 14.08 m of recorded advance, including core-recovery events. It demonstrates continued field use and follow-up. It is a single-pile record, not a measured lifetime for an unchanged set of roller bits.

Follow the 14.08 m pile entry →

What did the trial deliver for the customer?

A purpose-built barrel, encouraging discharge feedback and a practical improvement plan grounded in site use. The customer’s wear problem was investigated through the complete cycle: tool geometry, rig operation, cuttings, core recovery and cutter condition.

Good cuttings discharge was reported

During the 6–7 June overnight entry, the operator described the new barrel’s discharge as good. That feedback supports the high-spiral design direction for this site. The same conversation identified core recovery after a short advance as a remaining constraint.

Operating adjustments produced a positive response

The site summary reports about 0.35 m/h after feed and speed adjustments, compared with the earlier 0.2–0.3 m/h described in the review. Several settings changed together, so this is a reported operating response, not a controlled comparison proving the high spiral alone increased penetration.

The next work was defined with the field evidence

The review identified three priorities: maintain the cuttings guides and slurry, improve core gripping and unloading, and keep each barrel’s usage and cutter-change record together. The dated inspections and eight pile entries provide a basis for that next trial. A verified service-life increase remains to be established.

For another contractor facing the same symptoms, the value is a tool and support plan matched to the site: review the existing assembly, choose the design changes, discuss operation with the crew and follow the results through drilling and inspection.

Discuss a similar problem on your site →

Field records

Expand the original pile entries, operating notes and inspection follow-up. Clock readings and recorded events remain together, including lifting, recovery and interruptions.

Trial configuration and rigs
Trial scope and site context
ItemRecorded detail
Trial tool800 mm high-spiral roller-bit core barrel with revised cutter spacing
Detailed trial period5–9 June 2025; 8 named pile entries
Rigs in those entriesMachines 18, 3 and 13: XCMG XR360; machine 10: Sany SR360
Wider site800 and 1,000 mm piles; 16 rigs listed in the site overview
Assembly trackingTools moved between rigs; a further reaming transfer to machine 12 is noted separately
Open all eight pile entries
Per-pile work from the detailed June log
Pile / machineDateRecorded advanceOperation / observation
A3-11-2 / 185 June≈1.00 mReaming a hole made by a bullet-tooth barrel; about 10 minutes in the summary
ZH-16 / 35–6 June5.83 mDepth 8.90 → 14.73 m; field-measured head speed 14–15 r/min
ZH-30 / 136 June2.50 mDepth 8.44 → 10.94 m; stops and lifting recorded
Zz-K4G2-17 / 106 June0.43 mDepth 12.58 → 13.01 m; slight vibration recorded
Zz-K4G2-8 / 106–7 June2.04 mDepth 11.06 → 13.10 m; inclined rock reported
Zz-K5G1-5 / 107 June0.57 mDepth 16.46 → 17.03 m; stronger vibration and high tool temperature reported
Zz-K4G2-16 / 107 June1.02 mDepth 12.16 → 13.18 m; core recovery and moving to another pile
A1-11-2 / 107–9 June14.08 mDepth 6.85 → 20.93 m; lifting, core recovery and pauses logged

The first row is reaming. Later rows include different ground and sequences; 14.08 m belongs to one pile entry.

Elapsed windows and cumulative totals
Two complete elapsed windows
PileStart → endCalculated elapsed-window rate
ZH-1619:58 → next day 06:08; 5.83 m / 610 min0.57 m/h
ZH-3009:30 → 15:20; 2.50 m / 350 min0.43 m/h
Mileage accounting at the last detailed update
FigureWhat it includes
27.47 m calculated from the 8 rows aboveIncludes the approximately 1 m initial reaming entry
28.47 m reported cumulative in the detailed logThe log also notes reaming from about 5 m to 6 m on machine 12, without a separate exact row
21.61 m in the overview tableAn earlier/incomplete running total; it does not match the last detailed update

Calculated elapsed-window rate = recorded depth advance × 60 ÷ elapsed minutes. The windows include lifting or pauses. The 28.47 m is the log’s reported running total. The transfer record and individual replacements remain unresolved; this is not an unchanged-set service-life figure.

Recorded observations and proposed follow-up
Recorded observation and follow-up focus
ObservationWorking explanation / next checkResponse status
First hole too small for the new barrelConfirm the swept cutting diameter before introducing a different toolMoved to a fresh pile after initial reaming
Ground changed sharply between holesSeparate intact rock, boulders/interlayers and clearing in the logGround and recovered-core observations recorded
Worn guides on existing tools; thick or insufficient fluid at timesInspect guide condition and clearing/fluid practiceMaintenance and fluid-review actions proposed
Tools shared among rigs; new and used components mixed on siteAssign tool/cutter IDs and start a new mileage segment at replacementMore consistent tool and replacement records proposed
The parameter adjustment described in the site summary
Parameter change described in the site summary
FieldBefore the adjustment, as reportedAfter the adjustment, as reported
P4 hydraulic-pressure indication2–3; unit not given5–6; unit not given
Head speed10–12 r/minApproximately 15 r/min
Y-axis inclination0.3°0.6°
Rate described by the author as pure cutting0.2–0.3 m/h0.35 m/h

The adjustment is described in the site summary without a paired pile ID or start/end interval. It reports a modest change in cutting rate after several settings changed together; it does not establish a transferable setting or a measured percentage improvement. The separate 0.4–0.5 m/h reference was experience from other sites, not this trial. Manual rope payout was proposed for a later check.

Depth checkpoints, rig by rig

Open a pile to see the original clock readings, depths and work events. Rates below are the source-entered values, not newly calculated pure-cutting rates. Lifting, recovery, meal breaks and rig moves remain visible. A dash means the field was blank in the source.

ZH-16 · machine 3 · 5–6 June 2025 · 8.90 → 14.73 m
ZH-16 · machine 3 · 5–6 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
19:588.90Barrel lowered
20:369.601.110.7
20:5510.041.391.14Tool lifted
21:2510.721.361.82
21:5511.321.22.42
22:0411.662.32.76Tool lifted
22:3211.960.643.06Barrel lowered
23:0512.340.693.44
0:1712.640.543.74
1:2013.060.44.16
2:3313.540.394.64
6:0814.730.335.83Pile completed

Field-measured head speed: 14–15 r/min. The separate lowering note says 19:57; the first depth row is 19:58.

ZH-30 · machine 13 · 6 June 2025 · 8.44 → 10.94 m
ZH-30 · machine 13 · 6 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
9:308.44Barrel lowered
10:159.761.761.32Tool lifted
10:379.820.161.38Barrel lowered
11:119.940.211.5No additional crowd applied; drilling under assembly weight
11:3010:00 (as written)*0.191.56Drilling stopped
13:0410.341.9Tool lifted
13:5910.600.282.16Tool lifted
15:0010.840.242.4
15:2010.940.32.5Pile completed

At 11:11 the log records no additional crowd. *The 11:30 depth cell is written “10:00”; it has not been silently changed to a decimal.

Zz-K4G2-17 · machine 10 · 6 June 2025 · 12.58 → 13.01 m
Zz-K4G2-17 · machine 10 · 6 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
16:3412.58Barrel lowered
17:1312.750.260.17Slight vibration; broken rather than intact rock suspected
17:2512.830.40.25Tool lifted
17:2912.830.25Barrel lowered
17:5113.010.490.43Pile completed

The 17:25 lift and 17:29 lowering remain separate events.

Zz-K4G2-8 · machine 10 · 6–7 June 2025 · 11.06 → 13.10 m
Zz-K4G2-8 · machine 10 · 6–7 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
20:1711.06Barrel lowered
20:5911.080.0290.02
21:4211.320.330.26Tool lifted
23:2011.770.280.71
2:4112.690.271.63
3:3413.10.462.04Pile completed

The table starts at 20:17 / 11.06 m. A separate operator account says a change from bucket to roller barrel at 23:06 / 10.1 m; that conflicting account is not merged into this sequence.

Zz-K5G1-5 · machine 10 · 7 June 2025 · 16.46 → 17.03 m

View the two recovery attempts and the material brought up

Zz-K5G1-5 · machine 10 · 7 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
8:3016.46Barrel lowered
9:0916.890.660.43
9:2016.950.330.49Stronger vibration
9:3617.030.30.57Tool lifted

The first and second core-recovery photographs and original first-attempt video belong to this pile entry.

Zz-K4G2-16 · machine 10 · 7 June 2025 · 12.16 → 13.18 m
Zz-K4G2-16 · machine 10 · 7 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
10:5212.16Rock entry began
11:0612.320.690.16E mode; steady rock entry; 9 r/min; wire-rope entry 5 t; P4 2.7 (unit omitted); Y-axis entry “0.2 -0.3” (sign/range and unit unconfirmed)
11:2912:46 (as written)*0.370.3Drilling stopped
11:50Barrel lowered
13:5713.181.02Core recovery; move to another pile

*The 11:29 depth cell is written “12:46”. The operator later reported a display reset after lunch and readings roughly 0.1 m below actual depth; the original readings remain unchanged.

A1-11-2 · machine 10 · 7–9 June 2025 · 6.85 → 20.93 m
A1-11-2 · machine 10 · 7–9 June 2025 · original depth log
Local timeDepth, mSource-entered rate, m/hSource-entered pile advance, mRecorded event
18:046.85
18:277.120.70.27
18:577.240.240.39
20:117.400.130.55Some roller-bit jumping recorded
21:337.670.20.82Tool lifted
23:258.240.31.39
00:568.650.271.8Core recovery
2:429.480.472.63
3:559.990.423.14
7:0410.630.23.78
9:1011.060.24.21Core recovery
9:2811.140.274.29Barrel lowered
10:1311.400.354.55Lift / core recovery
10:5411.520.184.67
11:30-11:50Tool lifted; operator meal break
12:4511.754.9
12:51Rig moved; drilling stopped
13:01Barrel lowered
13:2711.955.1
13:3811.990.225.14Tool lifted
13:5311.99Drilling resumed
14:1512.100.35.25Rotary-speed entry: 14 r/h as written; unit needs confirmation
14:5212.300.325.45
15:0112.340.27Tool lifted
15:10Drilling resumed
16:1812.79
16:2412.830.45.98
16:5412.990.326.14Tool lifted
17:2612.99Lift / core recovery
17:4613.100.336.25
17:52Tool lifted; boulder layer possibly penetrated; roller barrel lowered again
18:0513.146.29
18:3013.320.436.47
19:0113.480.316.63
20:3913.790.196.94
21:4714.070.257.22
22:2914.710.917.32Log reports inclined rock penetrated
00:5515.160.198.31
1:5715.440.278.59
3:0215.710.258.32
4:1616.010.249.16
5:0416.260.319.41
5:5817.150.9910.3
8:3819.050.7112.2
9:3819.850.813
10:1120.230.6913.38
11:1320.930.6814.08Tool lifted

Clock rows run across two midnights. The source-entered pile-advance values at 22:29 (7.32 m) and 03:02 (8.32 m) do not reconcile with depth minus 6.85 m. The 14:15 speed unit is written “14 r/h”; it is not converted into rpm.