Guangdong · 5–6 December 2023 · B47K22 trial

Changing the method when cuttings build up.

DRILLNOVA · Field report · Updated

During a B47K22 trial in a 1,200 mm pile, the operator encountered high resistance. Lifting the core barrel revealed packed cuttings, while an earlier inspection had found uneven outer-tooth wear and one tooth that could not rotate.

The crew cleared the hole, reviewed the recovered ground and changed to direct breaking and clearing with the 1,200 mm bucket. The site note reports faster progress after this change. This case shows how an inspection led to a practical change of method, alongside the separate review of tooth condition.

See the field decision and result →

Bullet-tooth core barrel lifted beside the pile opening at the Guangdong site
The lifted bullet-tooth barrel at the trial site, with the bore and rig visible.

The result is the site team’s observation after changing the working method. The photographs and depth record below explain the decision; there is no timed before-and-after comparison.

Define the cutting and clearing stages.

A Sany 405R worked pile T-47 with a 1,000 mm B47K22 core barrel and a 1,200 mm drilling bucket. The barrel cut the rock; the larger bucket enlarged and cleared the 1,200 mm pile. The initial ground was recorded as moderately weathered gneiss in a water-filled hole.

View from the cab as the trial barrel is lowered into the hole
The trial setup photographed from the cab; the tool roles are recorded in the site log.

14:32 → 14:35 · record the cutting interval.

Guangdong rig display at 14:32 showing 7.96 m
14:32 · 7.96 m. Start of the recorded short cutting interval.
Guangdong rig display at 14:35 showing 8.17 m
14:35 · 8.17 m. The 0.21 m increase took 3 cutting minutes.

Two cab photographs anchor the 7.96–8.17 m interval. The later lifts exposed the outer teeth and accumulated material. Read the settings below with those inspection points.

Cutting and lifting decisions · 6 December 2023
Stage / depthHead speed, r/minP4 indication*Field action
14:32 → 14:35 · 7.96 → 8.17 m7.4 → 65.5 → 5.3–60.21 m in 3 effective cutting minutes.
14:47 · 8.83 mNot recorded at liftNot recorded at liftLifted and inspected the outer teeth before the next run.
15:01 · 9.22 mNot recorded at liftNot recorded at liftLifted after high resistance; changed to bucket clearing when packed material was found.

*P4 units were omitted in the source. The complete checkpoint table below retains the readings without converting them to force.

Subsequent readings at 8.47 and 8.67 m, plus the Y-axis readings, are retained in the complete operating table below.

The first lift exposed a tooth-rotation problem.

At 14:47 and 8.83 m depth, one outer tooth could not rotate and all outer teeth showed uneven wear. The team recorded the condition of the teeth on the lifted barrel. This made the affected area clear for a tooth-and-holder review; it did not isolate the cause of the rotation problem.

Uneven wear on an outer bullet tooth during the Guangdong trial
Outer-tooth wear documented during the trial inspection.

The next lift explained the immediate clearing decision.

At 15:01 and 9.22 m, the operator reported high resistance. Lifting revealed heavy cuttings build-up around the cutting assembly. The crew changed to the bucket to clear the hole, so the material and the drilling response could be reviewed together.

Mud and packed cuttings on the bullet-tooth barrel after lifting
The later lift exposed accumulated material around the cutting assembly.

The recovered ground changed the working method.

The crew considered the cleared material and the cutting response, and judged the rock to be more weathered. They changed from the barrel-and-bucket sequence to direct breaking and clearing with the 1,200 mm bucket.

The site note reports faster progress after the change. It is a useful result of matching the method to the observed ground. The record does not quantify the gain or attribute it to the B47K22 teeth alone.

Recovered weathered rock material from the Guangdong trial
The recovered material informed the method review alongside the tool inspection.

What did the on-site review change?

The crew acted on what the lifted tool and recovered material showed, and the record reports faster progress with the revised method. The case connects a drilling symptom to an inspection, a clearing action and a practical decision about the next tool.

One problem prompted an immediate action.

Heavy resistance led to a lift at 9.22 m. Visible cuttings build-up led to bucket clearing. The recovered material then supported the decision to continue with direct bucket breaking and clearing in the more-weathered ground.

The tooth condition remained a separate technical review.

The non-rotating tooth and uneven wear were photographed and retained in the record. Changing the working method does not show that the rotation problem was repaired. The next tooth review still needs the holder condition, freedom of rotation and installed arrangement.

A useful decision for another site.

When resistance rises or material packs around the cutters, a tool selection can depend on the recovered ground as much as the tooth specification. Bring those observations into the same review so the next decision covers both the replacement part and the working sequence.

Discuss your tool and clearing sequence →

The operating log and inspection decisions

Pile, trial teeth and project context
T-47 configuration in the December 2023 trial
ItemRecorded detail
Trial pile / rigT-47; Sany 405R
Pile and paired tools1,200 mm pile; 1,000 mm bullet-tooth core barrel + 1,200 mm drilling bucket
Trial teethB47K22; carbide written as 22 × 27 mm in this trial record
Fluid / initial rock descriptionWater-filled hole; moderately weathered gneiss
Recorded rock entry / final hole depth7.58 m / 10.04 m
Wider project register170+ piles across 1,000, 1,200 and 1,400 mm diameters; 25-day period stated in the project notes

The 170+ piles and 25-day period describe the wider project, not this tooth set. The 22 × 27 mm carbide entry belongs to the historical trial batch; current supply follows the selected drawing.

Open the depth and lift sequence
Recorded operating sequence for T-47
TimeHole depthRecorded operation / observation
13:35Prepared B47K22 test barrel fitted
14:327.96 mHead speed 7.4 r/min recorded
14:358.17 m0.21 m over the preceding 3 minutes; head speed 6 r/min
14:398.47 mHead speed 6.3 r/min
14:438.67 mHead speed 5.8 r/min
14:478.83 mLift and inspection: 1 outer tooth stuck; all outer teeth showed uneven wear
14:55 → 14:588.83 → 9.17 mBarrel lowered and drilling resumed
15:019.22 mHigh resistance reported; tool lifted and packed cuttings found
After liftingBucket used to clear; recovered material and drilling response led to direct breaking/clearing with the 1,200 mm bucket
Observed condition, action and unresolved question
Observation, action and remaining question
ObservationAction recordedQuestion for the next review
1 non-rotating outer tooth and uneven wear across the outer teethTool lifted and tooth condition photographedWhich tooth/holder positions were affected, and did free rotation return after cleaning?
Heavy packed cuttings on the later liftChanged to the bucket to clear the holeHow did cuttings and fluid condition change between lifts?
Recovered material appeared more weatheredChanged to direct breaking and clearing with the 1,200 mm bucketRecord the next timed cycle under the changed method
Pressure, head speed and depth at each recorded check

6 December 2023 · T-47 · Sany 405R. The retained cab photos show the date. These are observed settings in this pile; blank fields below mean that the log did not give a reading.

T-47 operating readings and lifting events
Local timeDepth, mHead speed, r/minP4 reading*Y-axis inclination, °Recorded event
14:327.967.45.5-0.4Cutting checkpoint
14:358.1765.3–6-0.30.21 m in 3 effective cutting minutes
14:398.476.36.7-0.4Cutting checkpoint
14:438.675.86.3-0.4Cutting checkpoint
14:478.83Not recordedNot recordedNot recordedLift and tooth inspection
14:558.83Not recordedNot recordedNot recordedBarrel lowered
14:589.17Not recordedNot recordedNot recordedCutting checkpoint
15:019.22Not recordedNot recordedNot recordedHigh resistance; lift and change to bucket clearing

*The source omits the P4 unit. Values are reproduced without converting hydraulic pressure into drilling force. The 14:35 photograph shows an instantaneous P4 value of 5.6; the written 5.3–6 is an interval range. The 7.96–8.17 m entry is explicitly 3 effective cutting minutes; other clock spans include only the work indicated in the event column and are not labelled pure cutting time.