MH-3 Roller Bit Life: Metres Drilled and Cost per Metre

DRILLNOVA · Technical guide · Updated

Around 35–50 metres is a practical field-experience reference for a set of MH-3 roller bits working in granite at approximately 100–150 MPa. This range comes from DRILLNOVA’s past site feedback. Use it as a starting point for planning; the barrel arrangement, rock abrasivity, drilling practice and cutter condition affect the result.

01 / FIELD EXAMPLE

Zengcheng: 1,200 mm barrel, 10 MH-3 roller bits

At this Guangzhou site, the customer’s existing core barrel was rebuilt with 10 MH-3 roller bits—five inner and five outer—and four scrapers. It worked on a SANY 415R rig. The June–August 2022 follow-up reached approximately 57 m of cumulative drilling.

The first visit described monzogranite / granite-amphibolite and estimated strength at 100–200 MPa. Later notes recorded weathered mudstone through moderately and slightly weathered gneiss. These are site descriptions, rather than laboratory UCS results for one uniform rock interval.

The case therefore adds a real barrel configuration and drilling history to the 35–50 m experience reference above.

Customer’s 1,200 mm core barrel after the MH-3 rebuild at Zengcheng
The existing barrel after the June 2022 rebuild. Ten MH-3 roller bits and four scrapers were fitted.

02 / RECORDED METRES

What did the site record?

Zengcheng follow-up · 2022
Inspection dateCumulative advance
26 August≈45.9 m
30 August≈51 m
31 August≈57 m

The 45.9 m total combines 35.9 m in earlier records + approximately 4 m estimated for four unlogged piles + 6 m drilled on 24–25 August. The later totals are rounded site updates.

At about 45.9 m, the position-by-position inspection identified three roller bits needing replacement. The complete replacement timing is not recorded, so the 57 m total describes the barrel’s cumulative work, not a verified unchanged-set life.

Original handwritten Zengcheng log listing pile identifiers and drilled metres
Original pile-by-pile drilling record. Open the image to read the entries; the additional estimated metres are explained alongside it.

03 / CONDITION IN SERVICE

Real wear at two inspection stages

Early MH-3 roller-bit condition at the approximately 1.2 m inspection on 30 June 2022
30 June · approximately 1.2 m. The site note recorded light cone-back wear, with the inserts and leg in good condition.
Outer roller-bit position 5 at the approximately 45.9 m cumulative inspection on 26 August 2022
26 August · approximately 45.9 m cumulative. Outer position 5 was recorded as having acceptable overall wear. This photograph shows one position, not the condition of all ten.

The photographs show different positions at the two inspections; they do not track one identified roller bit over time. Condition differed by position: outer 2 and inner 2 had seized bearings; outer 3 had more insert breakage. The review identified these three for replacement while assessing the other positions individually. See all ten inspection positions in the complete case.

04 / OPERATING CONTEXT

The operating record behind the metres

On 1 July, the depth display moved from 22.67 m to 27.46 m: 4.79 m of advance between 12:59 and 18:24. That is the complete work window, including interruptions and handling, rather than continuous cutting time.

The same entry recorded 6–7 rpm on initial rock entry, then 8–10 rpm after stable contact. These are settings recorded on that rig and job, not universal operating instructions. The field review also addressed cuttings removal and fragments left after core recovery.

For your own project, start with the 35–50 m MH-3 reference for 100–150 MPa granite, then compare the barrel diameter, cutter count, rock condition and operating sequence. Record replacements by position so that cost per metre uses the actual cutters consumed and the corresponding drilled interval.

05 / COST PER METRE

How do you calculate roller-bit cost per metre?

Roller-bit cost per metre = cost of roller bits consumed in the recorded interval ÷ metres drilled in that same interval. Use actual replacement and drilling records. The 35–50 m experience range is a planning reference; it does not establish the cost achieved on your job.

Keep one record for each defined drilling interval
RecordWhat to include
Ground and advancePile or hole ID, depth from and to, rock description, actual metres, barrel diameter and rig.
Roller bits consumedModel, numbered position, installation and removal points, quantity, unit cost and reason for replacement. Account consistently for cutters already partly used at the start or still usable at the end.
Other tool costsRecord removal, fitting or welding, and repair separately. If downtime is costed, state the time and rate used; keep this distinct from cutter-only cost.
Basis for comparisonUse the same currency, cost scope and drilling interval. Pair the record with wear photos and note changes in ground or operating method.

A barrel’s cumulative advance does not show how far every individual roller bit has worked. The Zengcheng record does not contain a complete replacement-cost ledger, so it supports a field review rather than a verified cost-per-metre figure.