Zengcheng · 1,200 mm rotary piling · June–August 2022

Replacing roller bits while keeping the existing core barrel

DRILLNOVA · Field report · Updated

At the Zengcheng site, our team helped replace the roller bits on a customer’s existing 1,200 mm core barrel supplied by another company. The work covered measurement, MH-3 positioning, welding guidance, operator handover and dated follow-up inspections. Approximately 57 m was recorded cumulatively for the assembly after replacement; this is not the service life of one unchanged cutter set.

See the results and support delivered → · Compare piling roller bits

Refitted core barrel suspended beside the rig during the 30 August field follow-up.
30 August · the barrel after roller-bit replacement, during the approximately 51 m follow-up. The case continued to approximately 57 m by 31 August.
Two people wearing safety helmets beside the drilling rig in the Zengcheng site-visit record
Site visit photograph from the Zengcheng follow-up record.

DRILLNOVA · FIELD SUPPORT

On-site fitting and operator guidance

The customer invited our team to work on its existing barrel. Our assignment covered measurement, roller-bit positioning and welding guidance, followed by practical discussions with the operators about entry, loading, speed and cuttings clearance.

See the positioning and welding record →
Follow the operator handover and drilling checks →

23–24 June · understand the existing tool and the problem

The customer asked us to assess a barrel and original roller bits that had not been supplied by our team. The operator reported repeated cone loss and increased vibration. Our assignment was to improve the use of this existing tool, starting with its geometry, the operating practice and the material around the cutters.

Before our involvement · the customer’s original cutting assembly, supplied by others.
Before our involvement · the customer’s original cutting assembly, supplied by others.
Team member measuring the existing Zengcheng barrel opening
Measure the existing opening before reusing the shell.

The nominal 1,200 mm barrel had ten roller bits and no scrapers. The initial notes recorded a 1,080 mm cutting-ring diameter, seized outer cutters, inner cone wear and uneven spiral wear. The ring dimension describes the steelwork, not the maximum cutting diameter.

On 24 June, we measured the retained shell and the companion bullet-tooth barrel. The guide wear and the shell’s joined construction raised a question about alignment between the cutting ring and the drive connection. That mattered before choosing a centre reference for the new cutters.

We also checked the recovered rock, the displayed operating parameters and the limited fluid supply. Packed cuttings, heat and the operator’s preferred speed/load were investigated alongside the tool geometry; the first visit did not establish a single cause for the missing cones.

Original tool, ground observations and survey dimensions
23 June · close-up of the original barrel shell and worn spiral guides.
23 June · close-up of the original barrel shell and worn spiral guides.
Original barrel and MH-3 replacement arrangement
ItemRecorded detail
Rig / nominal barrelSany 415R; 1,200 mm core barrel
Existing cutting ring1,080 mm diameter recorded at the initial visit
Original assembly10 roller bits; no scrapers
Replacement configuration10 MH-3 roller bits + 4 scrapers; existing shell retained
Site work26–27 June 2022; cutouts/spacers prepared, centre set, cutters positioned and welded; spirals partly repaired

The initial site feedback of 40–50 m concerned the old assembly. It is background to the replacement work, not a matched comparison with the later MH-3 work.

The first visit described the samples as monzogranite / granite-amphibolite and estimated 100–200 MPa; the 30 June notes described weathered mudstone through gneiss. These are dated field descriptions, not a laboratory UCS certificate or a verified uniform rock interval.

A roller-bit replacement and cuttings-clearance plan

The initial plan retained the shell and specified ten MH-3 roller bits with four scrapers. Spiral-guide repair, operating adjustments and better mixing of cuttings with the drilling fluid were part of the same discussion.

Initial proposal · the layout recorded after the first site survey.
Initial proposal · the layout recorded after the first site survey.
From site observation to a proposed change
Site observationProposed responseWhat happened
Existing ten-cutter arrangement without scrapersFit ten MH-3 roller bits and four scrapersCompleted during the 26–27 June replacement work
Worn spiral guides and packed materialRestore guide height and improve material clearanceOnly partial spiral repair was completed under site constraints
Vibration and uncertain operating conditionsReview entry speed, loading and fluid/clearing practice with the operatorObserved again during the 30 June–1 July runs; adjustments remained specific to the site

On 25 June, the team arranged the scraper and spiral parts with the fabricator, booked the welder and coordinated the site equipment. The record distinguishes the original proposal from what could actually be built on site.

26–27 June · turn the plan into a fitted assembly

The welding record follows the job through preparation, fitting, positioning and completion. The critical checks happened before the final welds, while the cutter height and position could still be corrected.

Preparing the Zengcheng site work area for roller-bit replacement
26–27 June: preparing the site work area for roller-bit replacement.

Prepare the opening and cutter projection

The crew cleaned the cutting ring, checked its diameter and compared the old weld openings with the MH-3 leg. They then trimmed the openings, cut the spacers and rechecked the planned cutter projection before fixing the spacers.

26 June · checking the trimmed opening with a rule and square during spacer preparation.
26 June · checking the trimmed opening with a rule and square during spacer preparation.
Centre reference being measured inside the prepared Zengcheng barrel
Set the centre reference before fixing cutter positions.

Establish the centre, then position and weld

A steel-bar reference was used to locate the barrel centre. The team rechecked that reference, then controlled the design positions while the welder tack-fixed the roller bits. Full welding followed, with attention to heat transfer and cooling around the roller-bit assembly.

26 June · positioning an MH-3 roller bit against the agreed reference.
26 June · positioning an MH-3 roller bit against the agreed reference.
26 June · continuing the site welding after dark, following the earlier power interruptions.
26 June · continuing the site welding after dark, following the earlier power interruptions.
26–27 June: welding sequence and control-point record

End-of-day condition: guide-strip work remained incomplete

Power interruptions pushed the remaining work into 27 June. The new roller bits and scrapers had been fitted, but the guide-strip repair was still incomplete when the photograph below was taken. It records the end of that day’s work, not a fully finished barrel. Approximately 10 mm variation in scraper bevel cuts also prompted a proposal to agree the geometry and pre-cut parts in the workshop for the next job.

Refitted MH-3 core barrel at the Zengcheng site
27 June · end-of-day assembly state. The roller bits and scrapers were fitted; the guide-strip work was not fully welded.
Recorded site sequence
Time / dateRecorded workControl point
26 June · 08:27Prepare a level work area and steel plateProvide a stable surface for rotating and positioning the barrel
08:47–09:25Clean the cutting ring and remove loose rust; measure its diameterAssess the retained ring before cutting
09:29–11:05Compare old openings with the MH-3 leg; plan projection; cut out old cuttersCheck the opening size and the intended spacer height
11:10–13:44Finish the openings, size and fix the spacersRecheck the intended cutter projection
13:50–14:22Establish the centre with the steel-bar referenceTeam recheck before locating the cutters
14:26–15:10; 17:34–19:27Position and tack-fix the roller bitsWelder places the parts; team checks the design positions
19:29–20:12; 21:00–22:08Full weldingMonitor heat transfer and cooling around the roller bits
27 June · 09:39–11:00; 12:08–16:11Fit scrapers and partly repair the spiralsInspect bevel-cut consistency and heat exposure near the cutters

Power interruptions occurred between the recorded working windows. The diary records cooling precautions, but does not provide a qualified welding procedure, welding temperature limits or a complete weld-acceptance record. Those must be agreed for the actual assembly.

30 June–1 July · follow the drilling and recovery cycle

The next visits followed the rebuilt tool back into the hole. The observations connected drilling, lifting, recovered material and cutter inspection, so the next adjustment could respond to what was happening at the working face.

30 June · weathered material examined during the ground observations.
30 June · weathered material examined during the ground observations.
1 July · recovered core and rock fragments documented during the drilling follow-up.
1 July · recovered core and rock fragments documented during the drilling follow-up.

Leave the operators with a usable method

The on-site work included practical training for the crew. We showed the team how to establish the centre reference and position the roller bits, then discussed entry, speed and loading, fluid supply, and clearing the cutting face with the operators. The incoming operator was also briefed so the operating approach could continue across the handover.

On 30 June, the operator recognised the effect of insufficient water on packed cuttings. The team discussed increasing fluid supply, reducing speed for the observed rock interval and clearing the cutters between advances. The 1 July log distinguished initial entry from stable drilling. The follow-up analysis recommended gentler re-entry after core recovery; it did not record a controlled result for that proposed change.

30 June · compare the operating response

After about 1.2 m, the carbide inserts and legs remained in good condition, with light wear on the cone and its back. Relatively dry material was packed around the cutters. The team discussed fluid supply and clearing with the operator, alongside a lower-speed operating trial.

30 June: instrument photographs and two short operating windows
30 June · 19:36, displayed depth 26.69 m. One instrument photograph from the first operating observation.
30 June · 19:36, displayed depth 26.69 m. One instrument photograph from the first operating observation.
30 June · 19:45, displayed depth 26.84 m. One instrument photograph from the second operating observation.
30 June · 19:45, displayed depth 26.84 m. One instrument photograph from the second operating observation.

Each photograph belongs to a different observation below; the two images are not the start and finish of one timed run.

30 June: short observations before the 1 July record
Head speedP4 channel readingRecorded advance / elapsed
11–15 r/min5.0–6.00.11 m displayed / 10 minutes
8–10 r/min7.0–8.00.09 m / 6 minutes

The first advance was also estimated at about 0.12 m; the table retains the displayed 0.11 m. The two windows are site observations, not a controlled productivity test. P4 is a machine-display channel; the diary’s estimated total tonne loads were not calibrated as force at the cutters.

What rock was encountered?

23 June · rock-core section examined at the initial site survey.
23 June · rock-core section examined at the initial site survey.
23 June · close view of the rock texture recorded during the same survey.
23 June · close view of the rock texture recorded during the same survey.

The site notes used different rock descriptions at different visits: monzogranite / granite-amphibolite for the initial samples, then weathered mudstone through moderately and slightly weathered gneiss on 30 June. The 1 July run was described as slightly weathered rock. These field descriptions do not establish one uniform granite interval for the full 50+ m follow-up.

1 July · follow entry through to the final depth

The log records a design pile depth of 26.89 m and rock entry at 21.66 m, where the bullet-tooth barrel could no longer advance. Initial roller-bit entry used 6–7 r/min. Once the face became stable, the recorded head speed was 8–10 r/min.

1 July: operating stages recorded at the rig
Recorded stageHead speedP4 channel reading
Initial rock entry · E1 mode6–7 r/min4.0–6.0
After the rock face became stable8–10 r/min5.0–8.0

These are the settings observed on that rig and interval, not universal operating limits for a 1,200 mm barrel. The logged window ran from 22.67 m at 12:59 to 27.46 m at 18:24: 4.79 m including intervening work.

30 June–1 July: cutter inspection photographs
MH-3 roller bit at the 30 June inspection after about 1.2 m
30 June · about 1.2 m at the early check. The source records light wear and serviceable carbide.
MH-3 roller-bit insert fracture marked in the original 1 July photograph
1 July · original red circle marks one broken insert. The inspection recorded three broken inserts in total.

After core recovery, the operator felt strong vibration on re-entry and large loose fragments. Three broken inserts and impact marks on the cone body were recorded at the 1 July inspection. This placed the previous recovery and tool change in the investigation, alongside ground conditions, clearing and the two barrels’ cutting paths. The record did not isolate one cause of the three broken inserts.

For a similar problem, record whether the first vibration appeared during continuous cutting or immediately after core recovery or a tool change. Keep the first damaged-position photo with that event. A photograph taken only at the end of the shift may miss the sequence that explains where to investigate.

Check the companion barrel as part of the same problem

The 1 July measurements were 1,200/110 mm for the bullet-tooth barrel and 1,180/120 mm for the roller-bit barrel: maximum cutting diameter / radial groove width. Cone-back wear, especially at the inner cutters, prompted a check of how these two cutting paths matched.

Two nominal 1,200 mm barrels can cut different rings

Using the 1 July dimensions and assuming both tools share the same centre axis, the bullet-tooth barrel cuts from a radius of 490 to 600 mm; the roller-bit barrel cuts from 470 to 590 mm. Their radial overlap is 490–590 mm. The roller-bit barrel therefore reaches farther inward, into the 470–490 mm band outside the first tool’s calculated path.

Whether that inner band actually contains rock depends on the core and bore-bottom condition when the tools are exchanged. The geometry explains what to measure; it does not prove that contact occurred. The 24 June record gives the bullet-tooth barrel a different outer diameter, about 1,180 mm. Using that earlier figure makes the inward difference 10 mm instead of 20 mm. Do not treat either difference as a measured interference or a machining allowance. For the next check, measure both inner and outer cutting diameters from a common axis and record which tool ran immediately before the vibration started.

Companion-barrel dimensions and calculation notes
Dated measurements of the paired barrels
Tool / record dateMaximum cutting diameterRadial groove widthCore diameter basis
Bullet-tooth barrel · 24 June≈1,180 mm110 mm≈960 mm recorded
Bullet-tooth barrel · 1 July1,200 mm110 mm980 mm calculated
MH-3 roller barrel · 1 July1,180 mm120 mm940 mm calculated

Calculated core diameter = maximum cutting diameter − 2 × radial groove width. The earlier 24 June bullet-barrel measurement differs from 1 July and remains in the dated record. The proposed contact mechanism was not independently verified.

The original 1 July narrative estimates 0.7 m/h. Its stated 4.79 m / 325-minute window calculates to 0.88 m/h. The reason for the difference is not recorded, so neither figure is presented as a proven speed improvement or a pure-cutting rate.

August · inspect every position and follow the running record

Follow-up continued after the site installation visits. The 26 August review combined the operator’s running record with a check of all five outer and five inner cutter positions. Its overall assessment was that condition after about 45 m was reasonably acceptable, while three abnormal positions required attention.

Two bearings were seized. Outer position 2 also had a cracked weld; outer position 3 had more extensive insert breakage. Replacement of the three abnormal roller bits and repair of the cracked weld were recommended. The favourable overall assessment did not mean these faults could be left in service.

View the photographs and notes for all ten positions →

The assembly’s cumulative drilling record after replacement reached about 51 m on 30 August and 57 m on 31 August. This follow-up showed how the customer continued using the existing barrel after the MH-3 roller-bit replacement. The same updates identified a heavily worn cutter and further insert breakage, which fed into the repair and design recommendations below.

Operator’s handwritten record and dated mileage history
Original handwritten pile-by-pile roller-bit usage notes photographed for the Zengcheng follow-up
The original handwritten usage notes referenced in the 26 August review. Pile IDs and metres are retained; no replacement history is added to the source.
Mileage and condition at each recorded stage
Date / stageRecorded work or running totalCondition / interpretation
30 June≈1.2 m at the early inspectionCarbide and legs in good condition; light cone/back wear
1 July22.67 → 27.46 m between 12:59 and 18:24: 4.79 m in the logged window3 broken inserts recorded; loose core fragments and paired-tool geometry considered
26 August≈45.9 m: 35.9 m from earlier records + ≈4 m estimated across 4 missing pile entries + 6 m on 24–25 August2 seized bearings and an outer weld crack; replacement of 3 abnormal roller bits proposed
30 August≈51 m running total; approximately 5 m added in the latest entryOne roller bit recorded as heavily worn; the author suspected the previously damaged cutter, but its position was not re-confirmed
31 August≈57 m running totalSevere outer insert breakage and further inner insert breakage recorded

About 45.9 m comprises 35.9 m from the earlier record, about 4 m estimated for four missing entries, and 6 m from 24–25 August. Later totals are approximate. Replacement history between these entries is not confirmed; 57 m is the last reported cumulative work, not a certified life for one unchanged set.

What did the customer gain from this work?

The customer gained an existing barrel fitted with replacement MH-3 roller bits, practical support for the site crew, and a dated record to guide the next maintenance decisions.

1. Put the existing barrel back to work

The original barrel and cutters had been supplied by others. Our team surveyed the retained assembly and helped fit ten MH-3 roller-bit positions and four scrapers. The customer continued using that barrel for rock drilling after replacement, with guide-strip finishing and further design refinements recorded separately.

2. Give the crew practical fitting and operating support

We worked with the site welder to establish the centre reference, check cutter positions and guide the welding sequence. Discussions with the operators connected the replacement work to rock entry, speed and loading, fluid supply and cuttings clearance. The customer received support for both the assembly and how it was used.

3. Follow the work through approximately 57 m

The 1 July log followed the barrel to the final depth, including 4.79 m of recorded advance between 12:59 and 18:24. Later updates reported approximately 45.9 m on 26 August, 51 m on 30 August and 57 m on 31 August. These are cumulative field records for the assembly after replacement, not a certified life for one unchanged roller-bit set.

At the approximately 45.9 m inspection, the overall assessment was reasonably acceptable, while three abnormal cutter positions and a cracked weld required attention. Follow-up turned these observations into specific repair and design proposals. The selected views below show two positions from that inspection; the complete ten-position record remains available.

Roller-bit condition after about 45.9 m

Two selected views from the last complete ten-position inspection. The notes described overall wear at these positions as acceptable; the full record below includes the positions that needed repair or replacement.

Outer 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Outer 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Inner 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Inner 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
View all ten positions · 26 August

Last complete position inspection · approximately 45.9 m. One photograph for each of the five outer and five inner positions, paired in the order used in the original inspection. These views precede the approximately 57 m update on 31 August.

Outer 1 · 26 August. Some broken inserts; bearing reported normal.
Outer 1 · 26 August. Some broken inserts; bearing reported normal.
Inner 1 · 26 August. Some broken inserts; bearing reported normal.
Inner 1 · 26 August. Some broken inserts; bearing reported normal.
Outer 2 · 26 August. Bearing seized; substantial wear and a weld crack recorded.
Outer 2 · 26 August. Bearing seized; substantial wear and a weld crack recorded.
Inner 2 · 26 August. Tooth wear described as acceptable; bearing seized.
Inner 2 · 26 August. Tooth wear described as acceptable; bearing seized.
Outer 3 · 26 August. More extensive insert breakage recorded.
Outer 3 · 26 August. More extensive insert breakage recorded.
Inner 3 · 26 August. Overall wear described as acceptable.
Inner 3 · 26 August. Overall wear described as acceptable.
Outer 4 · 26 August. A few broken inserts recorded.
Outer 4 · 26 August. A few broken inserts recorded.
Inner 4 · 26 August. Overall wear described as acceptable.
Inner 4 · 26 August. Overall wear described as acceptable.
Position-by-position condition recorded on 26 August
PositionCondition in the source inspection
Outer 1Some broken inserts; bearing reported normal
Inner 1Some broken inserts; bearing reported normal
Outer 2Bearing seized, substantial tooth wear; weld crack recorded
Inner 2Tooth wear described as acceptable; bearing seized
Outer 3More extensive insert breakage
Inner 3Overall wear described as acceptable
Outer 4A few broken inserts
Inner 4Overall wear described as acceptable
Outer 5Overall wear described as acceptable
Inner 5Overall wear described as acceptable

The review identified Outer 2, Inner 2 and Outer 3 for replacement, with a weld repair also required at Outer 2. Positions are the original inspection labels, not permanent serial numbers. The record does not confirm when these replacements were completed.

Remaining issues and next design proposals
What the field experience changed in the next proposal
FindingNext proposal in the original record
Site fitting consumed time and scraper cuts variedConsider a preassembled cutting ring with roller bits and scrapers; pre-cut bevels and confirm the retained shell dimensions
Dry, packed cuttings and steel wear around the coneReview taller/wider guides, top-plate clearing features and fluid/clearing practice
Cone-back wear and re-entry impactReview protective inserts on the cone back, companion cutting paths and re-entry after core recovery
Insert breakage was more prominent than uniform carbide wearConsider an MH-1 trial with fewer inserts to test cost per metre; this was a proposal, not an adopted or validated replacement
Operating practice affected the complete resultDevelop a practical operator guide and troubleshooting reference from the site observations
Completed work and proposed refinements
Evidence from the visitWork statusNext design question
10 MH-3 positions set, 4 scrapers added, spirals partly repairedCompleted on-site replacement workReview the proposed supply of a cutting ring assembled with roller bits and scrapers for a later rebuild.
About 10 mm variation noted in scraper bevel cuttingObserved during site workPre-cut bevels and agree the scraper geometry before installation
Packed, relatively dry cuttings and cone-back wearObserved during useReview guide height, fluid/clearing practice and the companion barrel’s cutting path
Bearing seizure, insert breakage and weld cracking at later inspectionsObserved; replacement/repair proposedKeep individual cutter IDs and record the work completed before the next mileage segment

For a new trial, record the rig and ground interval, cutter positions, each replacement, drilling and recovery time, and the next inspection decision. That connects measured output and wear to the actual configuration in use.