Zengcheng · 1,200 mm rotary piling · June–August 2022

On-site MH-3 refit: more than 50 m of recorded drilling.

DRILLNOVA · Field report · Updated

The customer’s original core barrel and roller bits were supplied by others. Faced with repeated cone loss and vibration, the customer invited our team to apply its drilling-tool experience on site.

We helped refit the existing barrel, guided cutter positioning and welding, trained the operators and followed the tool into service. The final follow-up recorded approximately 57 m of cumulative drilling with the refitted assembly.

See the results and support delivered →

31 August · the refitted barrel suspended at the borehole. The follow-up recorded approximately 57 m of cumulative drilling.
31 August · the refitted barrel suspended at the borehole. The follow-up recorded approximately 57 m of cumulative drilling.

23–24 June · understand the existing tool and the problem

The customer asked us to assess a barrel and original roller bits that had not been supplied by our team. The operator reported repeated cone loss and increased vibration. Our assignment was to improve the use of this existing tool, starting with its geometry, the operating practice and the material around the cutters.

Before our involvement · the customer’s original cutting assembly, supplied by others.
Before our involvement · the customer’s original cutting assembly, supplied by others.
Team member measuring the existing Zengcheng barrel opening
Measure the existing opening before reusing the shell.

The nominal 1,200 mm barrel had ten roller bits and no scrapers. The initial notes recorded a 1,080 mm cutting-ring diameter, seized outer cutters, inner cone wear and uneven spiral wear. The ring dimension describes the steelwork, not the maximum cutting diameter.

On 24 June, we measured the retained shell and the companion bullet-tooth barrel. The guide wear and the shell’s joined construction raised a question about alignment between the lower ring and the drive connection. That mattered before choosing a centre reference for the new cutters.

We also checked the recovered rock, the displayed operating parameters and the limited fluid supply. Packed cuttings, heat and the operator’s preferred speed/load were investigated alongside the tool geometry; the first visit did not establish a single cause for the missing cones.

Original tool, ground observations and survey dimensions
23 June · close-up of the original barrel shell and worn spiral guides.
23 June · close-up of the original barrel shell and worn spiral guides.
Original barrel and MH-3 refit
ItemRecorded detail
Rig / nominal barrelSany 415R; 1,200 mm core barrel
Existing cutting ring1,080 mm diameter recorded at the initial visit
Original assembly10 roller bits; no scrapers
Refit configuration10 MH-3 roller bits + 4 scrapers; existing shell retained
Site work26–27 June 2022; cutouts/spacers prepared, centre set, cutters positioned and welded; spirals partly repaired

The initial site feedback of 40–50 m concerned the old assembly. It is background to the refit, not a matched comparison with the later MH-3 work.

The first visit described the samples as monzogranite / granite-amphibolite and estimated 100–200 MPa; the 30 June notes described weathered mudstone through gneiss. These are dated field descriptions, not a laboratory UCS certificate or a verified uniform rock interval.

A refit plan for the customer’s existing barrel

The initial plan retained the shell and specified ten MH-3 roller bits with four scrapers. Spiral-guide repair, operating adjustments and better mixing of cuttings with the drilling fluid were part of the same discussion.

Initial proposal · the layout recorded after the first site survey.
Initial proposal · the layout recorded after the first site survey.
From site observation to a proposed change
Site observationProposed responseWhat happened
Existing ten-cutter arrangement without scrapersFit ten MH-3 roller bits and four scrapersCompleted during the 26–27 June refit
Worn spiral guides and packed materialRestore guide height and improve material clearanceOnly partial spiral repair was completed under site constraints
Vibration and uncertain operating conditionsReview entry speed, loading and fluid/clearing practice with the operatorObserved again during the 30 June–1 July runs; adjustments remained specific to the site

On 25 June, the team arranged the scraper and spiral parts with the fabricator, booked the welder and coordinated the site equipment. The record distinguishes the original proposal from what could actually be built on site.

26–27 June · turn the plan into a fitted assembly

The welding record follows the job through preparation, fitting, positioning and completion. The critical checks happened before the final welds, while the cutter height and position could still be corrected.

Preparing the Zengcheng site work area for the barrel refit
26–27 June: preparing the site work area for the barrel refit.
26 June · cleaning and measuring the lower ring before preparing the new cutter openings.
26 June · cleaning and measuring the lower ring before preparing the new cutter openings.

Prepare the opening and cutter projection

The crew cleaned the lower ring, checked its diameter and compared the old weld openings with the MH-3 leg. They then trimmed the openings, cut the spacers and rechecked the planned cutter projection before fixing the spacers.

26 June · checking the trimmed opening with a rule and square during spacer preparation.
26 June · checking the trimmed opening with a rule and square during spacer preparation.
Centre reference being measured inside the prepared Zengcheng barrel
Set the centre reference before fixing cutter positions.

Establish the centre, then position and weld

A steel-bar reference was used to locate the barrel centre. The team rechecked that reference, then controlled the design positions while the welder tack-fixed the roller bits. Full welding followed, with attention to heat transfer and cooling around the roller-bit assembly.

26 June · positioning an MH-3 roller bit against the agreed reference.
26 June · positioning an MH-3 roller bit against the agreed reference.
26 June · continuing the site welding after dark, following the earlier power interruptions.
26 June · continuing the site welding after dark, following the earlier power interruptions.

End-of-day condition: guide-strip work remained incomplete

Power interruptions pushed the remaining work into 27 June. The new roller bits and scrapers had been fitted, but the guide-strip repair was still incomplete when the photograph below was taken. It records the end of that day’s work, not a fully finished barrel. Approximately 10 mm variation in scraper bevel cuts also prompted a proposal to agree the geometry and pre-cut parts in the workshop for the next job.

Refitted MH-3 core barrel at the Zengcheng site
27 June · end-of-day assembly state. The roller bits and scrapers were fitted; the guide-strip work was not fully welded.
26–27 June: welding sequence and control-point record
Recorded site sequence
Time / dateRecorded workControl point
26 June · 08:27Prepare a level work area and steel plateProvide a stable surface for rotating and positioning the barrel
08:47–09:25Clean the lower ring and remove loose rust; measure its diameterAssess the retained ring before cutting
09:29–11:05Compare old openings with the MH-3 leg; plan projection; cut out old cuttersCheck the opening size and the intended spacer height
11:10–13:44Finish the openings, size and fix the spacersRecheck the intended cutter projection
13:50–14:22Establish the centre with the steel-bar referenceTeam recheck before locating the cutters
14:26–15:10; 17:34–19:27Position and tack-fix the roller bitsWelder places the parts; team checks the design positions
19:29–20:12; 21:00–22:08Full weldingMonitor heat transfer and cooling around the roller bits
27 June · 09:39–11:00; 12:08–16:11Fit scrapers and partly repair the spiralsInspect bevel-cut consistency and heat exposure near the cutters

Power interruptions occurred between the recorded working windows. The diary records cooling precautions, but does not provide a qualified welding procedure, welding temperature limits or a complete weld-acceptance record. Those must be agreed for the actual assembly.

30 June–1 July · follow the drilling and recovery cycle

The next visits followed the rebuilt tool back into the hole. The observations connected drilling, lifting, recovered material and cutter inspection, so the next adjustment could respond to what was happening at the working face.

30 June · weathered material examined during the ground observations.
30 June · weathered material examined during the ground observations.
1 July · recovered core and rock fragments documented during the drilling follow-up.
1 July · recovered core and rock fragments documented during the drilling follow-up.

Leave the operators with a usable method

The on-site work included practical training for the crew. We showed the team how to establish the centre reference and position the roller bits, then discussed entry, speed and loading, fluid supply, and clearing the cutting face with the operators. The incoming operator was also briefed so the operating approach could continue across the handover.

On 30 June, the operator recognised the effect of insufficient water on packed cuttings. The team discussed increasing fluid supply, reducing speed for the observed rock interval and clearing the cutters between advances. On 1 July, the log distinguished initial entry from stable drilling and recorded gentler re-entry after core recovery.

30 June · compare the operating response

After about 1.2 m, the carbide inserts and legs remained in good condition, with light wear on the cone and its back. Relatively dry material was packed around the cutters. The team discussed fluid supply and clearing with the operator, alongside a lower-speed operating trial.

30 June: instrument photographs and two short operating windows
30 June · 19:36, displayed depth 26.69 m. One instrument photograph from the first operating observation.
30 June · 19:36, displayed depth 26.69 m. One instrument photograph from the first operating observation.
30 June · 19:45, displayed depth 26.84 m. One instrument photograph from the second operating observation.
30 June · 19:45, displayed depth 26.84 m. One instrument photograph from the second operating observation.

Each photograph belongs to a different observation below; the two images are not the start and finish of one timed run.

30 June: short observations before the 1 July record
Head speedP4 channel readingRecorded advance / elapsed
11–15 r/min5.0–6.00.11 m displayed / 10 minutes
8–10 r/min7.0–8.00.09 m / 6 minutes

The first advance was also estimated at about 0.12 m; the table retains the displayed 0.11 m. The two windows are site observations, not a controlled productivity test. P4 is a machine-display channel; the diary’s estimated total tonne loads were not calibrated as force at the cutters.

What rock was encountered?

23 June · rock-core section examined at the initial site survey.
23 June · rock-core section examined at the initial site survey.
23 June · close view of the rock texture recorded during the same survey.
23 June · close view of the rock texture recorded during the same survey.

The site notes used different rock descriptions at different visits: monzogranite / granite-amphibolite for the initial samples, then weathered mudstone through moderately and slightly weathered gneiss on 30 June. The 1 July run was described as slightly weathered rock. These field descriptions do not establish one uniform granite interval for the full 50+ m follow-up.

1 July · follow entry through to the final depth

The log records a design pile depth of 26.89 m and rock entry at 21.66 m, where the bullet-tooth barrel could no longer advance. Initial roller-bit entry used 6–7 r/min. Once the face became stable, the recorded head speed was 8–10 r/min.

1 July: operating stages recorded at the rig
Recorded stageHead speedP4 channel reading
Initial rock entry · E1 mode6–7 r/min4.0–6.0
After the rock face became stable8–10 r/min5.0–8.0

These are the settings observed on that rig and interval, not universal operating limits for a 1,200 mm barrel. The logged window ran from 22.67 m at 12:59 to 27.46 m at 18:24: 4.79 m including intervening work.

MH-3 roller bit at the 30 June inspection after about 1.2 m
30 June · about 1.2 m at the early check. The source records light wear and serviceable carbide.
MH-3 roller-bit insert fracture marked in the original 1 July photograph
1 July · original red circle marks one broken insert. The inspection recorded three broken inserts in total.

After core recovery, the operator felt strong vibration on re-entry and large loose fragments. Three broken inserts were recorded at the 1 July inspection. The response was to review gentle re-entry, removal of loose fragments, and the relationship between the two barrels’ cutting paths.

Check the companion barrel as part of the same problem

The 1 July measurements were 1,200/110 mm for the bullet-tooth barrel and 1,180/120 mm for the roller-bit barrel: maximum cutting diameter / radial groove width. A groove cut by the first tool might interfere with the back of the following roller cones. This became a design check, rather than treating every broken insert as a cutter-material problem.

Companion-barrel dimensions and calculation notes
Dated measurements of the paired barrels
Tool / record dateMaximum cutting diameterRadial groove widthCore diameter basis
Bullet-tooth barrel · 24 June≈1,180 mm110 mm≈960 mm recorded
Bullet-tooth barrel · 1 July1,200 mm110 mm980 mm calculated
MH-3 roller barrel · 1 July1,180 mm120 mm940 mm calculated

Calculated core diameter = maximum cutting diameter − 2 × radial groove width. The earlier 24 June bullet-barrel measurement differs from 1 July and remains in the dated record. The proposed contact mechanism was not independently verified.

The original 1 July narrative estimates 0.7 m/h. Its stated 4.79 m / 325-minute window calculates to 0.88 m/h. The reason for the difference is not recorded, so neither figure is presented as a proven speed improvement or a pure-cutting rate.

August · inspect every position and follow the running record

Follow-up continued after the site installation visits. The 26 August review combined the operator’s running record with a check of all five outer and five inner cutter positions. Its overall assessment was that condition after about 45 m was reasonably acceptable, while three abnormal positions required attention.

Two bearings were seized. Outer position 2 also had a cracked weld; outer position 3 had more extensive insert breakage. Replacement of the three abnormal roller bits and repair of the cracked weld were recommended. The favourable overall assessment did not mean these faults could be left in service.

View the photographs and notes for all ten positions →

The refitted assembly’s cumulative record reached about 51 m on 30 August and 57 m on 31 August. This follow-up showed how the customer continued using the existing barrel after the MH-3 refit. The same updates identified a heavily worn cutter and further insert breakage, which fed into the repair and design recommendations below.

30 August · the barrel suspended at the borehole during the approximately 51 m follow-up.
30 August · the barrel suspended at the borehole during the approximately 51 m follow-up.
Operator’s handwritten record and dated mileage history
Original handwritten pile-by-pile roller-bit usage notes photographed for the Zengcheng follow-up
The original handwritten usage notes referenced in the 26 August review. Pile IDs and metres are retained; no replacement history is added to the source.
Mileage and condition at each recorded stage
Date / stageRecorded work or running totalCondition / interpretation
30 June≈1.2 m at the early inspectionCarbide and legs in good condition; light cone/back wear
1 July22.67 → 27.46 m between 12:59 and 18:24: 4.79 m in the logged window3 broken inserts recorded; loose core fragments and paired-tool geometry considered
26 August≈45.9 m: 35.9 m from earlier records + ≈4 m estimated across 4 missing pile entries + 6 m on 24–25 August2 seized bearings and an outer weld crack; replacement of 3 abnormal roller bits proposed
30 August≈51 m running total; approximately 5 m added in the latest entryOne roller bit recorded as heavily worn
31 August≈57 m running totalSevere outer insert breakage and further inner insert breakage recorded

About 45.9 m comprises 35.9 m from the earlier record, about 4 m estimated for four missing entries, and 6 m from 24–25 August. Later totals are approximate. Replacement history between these entries is not confirmed; 57 m is the last reported cumulative work, not a certified life for one unchanged set.

What did the customer gain from this work?

The customer put an existing barrel back into rock drilling with MH-3 roller bits, on-site installation support and a practical operating handover. The final update recorded approximately 57 m of cumulative drilling. The team’s assessment was that penetration was satisfactory for the conditions encountered; the 1 July log recorded 4.79 m over its timed operating window, including intervening work.

Roller-bit condition after about 45.9 m

Two selected views from the last complete ten-position inspection. The notes described overall wear at these positions as acceptable; the full record below includes the positions that needed repair or replacement.

Outer 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Outer 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Inner 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
Inner 5 · 26 August, approximately 45.9 m. Overall wear was described as acceptable.
View all ten positions · 26 August

Last complete position inspection · approximately 45.9 m. One photograph for each of the five outer and five inner positions, paired in the order used in the original inspection. These views precede the approximately 57 m update on 31 August.

Outer 1 · 26 August. Some broken inserts; bearing reported normal.
Outer 1 · 26 August. Some broken inserts; bearing reported normal.
Inner 1 · 26 August. Some broken inserts; bearing reported normal.
Inner 1 · 26 August. Some broken inserts; bearing reported normal.
Outer 2 · 26 August. Bearing seized; substantial wear and a weld crack recorded.
Outer 2 · 26 August. Bearing seized; substantial wear and a weld crack recorded.
Inner 2 · 26 August. Tooth wear described as acceptable; bearing seized.
Inner 2 · 26 August. Tooth wear described as acceptable; bearing seized.
Outer 3 · 26 August. More extensive insert breakage recorded.
Outer 3 · 26 August. More extensive insert breakage recorded.
Inner 3 · 26 August. Overall wear described as acceptable.
Inner 3 · 26 August. Overall wear described as acceptable.
Outer 4 · 26 August. A few broken inserts recorded.
Outer 4 · 26 August. A few broken inserts recorded.
Inner 4 · 26 August. Overall wear described as acceptable.
Inner 4 · 26 August. Overall wear described as acceptable.
Outer 5 · 26 August. Overall wear described as acceptable.
Outer 5 · 26 August. Overall wear described as acceptable.
Inner 5 · 26 August. Overall wear described as acceptable.
Inner 5 · 26 August. Overall wear described as acceptable.
Position-by-position condition recorded on 26 August
PositionCondition in the source inspection
Outer 1Some broken inserts; bearing reported normal
Inner 1Some broken inserts; bearing reported normal
Outer 2Bearing seized, substantial tooth wear; weld crack recorded
Inner 2Tooth wear described as acceptable; bearing seized
Outer 3More extensive insert breakage
Inner 3Overall wear described as acceptable
Outer 4A few broken inserts
Inner 4Overall wear described as acceptable
Outer 5Overall wear described as acceptable
Inner 5Overall wear described as acceptable

The review identified Outer 2, Inner 2 and Outer 3 for replacement, with a weld repair also required at Outer 2. Positions are the original inspection labels, not permanent serial numbers. The record does not confirm when these replacements were completed.

A working refit, backed by hands-on support

The scope covered the customer’s problem tool, its measurements and layout, assistance to the site welder, and checks of cutter positioning before full welding. The customer’s crew gained direct experience of the fitting references and control points. Guide-strip finishing remained a separate issue in the end-of-day photographs.

Operators who understood the operating approach

Training and handover connected the tool to its use: establish stable contact, adjust speed and loading to the drilling response, keep cuttings moving, and inspect after lifting. The incoming operator was included in the handover.

Follow-up that produced the next improvement decisions

At around 45 m, the field review described overall condition as reasonably acceptable and identified individual roller bits and a weld that needed attention. Continued reports through approximately 57 m led to proposals for better guide-strip clearance, companion-barrel geometry and cutter protection. This gave the customer specific actions to discuss for the next repair and drilling run.

For a contractor with a problem barrel, this case shows the support we can discuss: survey the existing assembly, define the refit, guide installation and operators, then follow the drilling and wear records.

Remaining issues and next design proposals
What the field experience changed in the next proposal
FindingNext proposal in the original record
Site fitting consumed time and scraper cuts variedConsider a preassembled lower ring with roller bits and scrapers; pre-cut bevels and confirm the retained shell dimensions
Dry, packed cuttings and steel wear around the coneReview taller/wider guides, top-plate clearing features and fluid/clearing practice
Cone-back wear and re-entry impactReview protective inserts on the cone back, companion cutting paths and re-entry after core recovery
Insert breakage was more prominent than uniform carbide wearConsider an MH-1 trial with fewer inserts to test cost per metre; this was a proposal, not an adopted or validated replacement
Operating practice affected the complete resultDevelop a practical operator guide and troubleshooting reference from the site observations
Completed work and proposed refinements
Evidence from the visitWork statusNext design question
10 MH-3 positions set, 4 scrapers added, spirals partly repairedCompleted site refitReview the proposed supply of a cutting ring assembled with roller bits and scrapers for a later rebuild.
About 10 mm variation noted in scraper bevel cuttingObserved during site workPre-cut bevels and agree the scraper geometry before installation
Packed, relatively dry cuttings and cone-back wearObserved during useReview guide height, fluid/clearing practice and the companion barrel’s cutting path
Bearing seizure, insert breakage and weld cracking at later inspectionsObserved; replacement/repair proposedKeep individual cutter IDs and record the work completed before the next mileage segment

For a new trial, record the rig and ground interval, cutter positions, each replacement, drilling and recovery time, and the next inspection decision. That connects measured output and wear to the actual configuration in use.